[#682]

A low overhead line may not mean a lower bid

When comparing custom-home bids, how do you tell whether a lower overhead and profit line reflects a genuinely lower total cost or costs folded into trade and material prices? I’d want to compare the same scope, but I’m not sure how consistently builders present these amounts.

What’s reasonable to ask each builder to clarify about general conditions, including whether supervision, temporary utilities, and site security are included? I’d also like to understand how the fee is calculated when allowances change or a change order adds work. Are there particular definitions or bid details that make these comparisons more reliable?


Join the conversation

Share your experience or ask a follow-up question.

6 replies

The fee base matters as much as the percentage. Ask each builder to show whether overhead and profit are calculated on direct costs and whether that fee also applies to general conditions, allowance overruns, and change orders. Those rules can make the same added cost produce different totals, so compare the stated calculation, not just the headline percentage.


Reply

A schedule of values can help show whether the low fee line reflects a lower total or costs carried elsewhere. It should separate trade and material costs from general conditions and the builder’s fee. If a trade quote is bundled, ask for its scope and exclusions too; otherwise, it’s hard to compare that bid with one that itemizes those costs.


Reply

A schedule of values can still leave general conditions too opaque if they’re shown as one lump sum. Ask for an itemized list with the basis and duration for each cost, especially supervision, temporary utilities, and site security. A monthly supervision charge and a separate utilities allowance make it easier to see whether a lower total assumes a shorter schedule or leaves services out.


Reply

A low trade number isn’t comparable if it covers less work or a different grade of materials. Do the bids spell out the same inclusions, exclusions, quantities, and quality assumptions for major items? I’d want those defined side by side before treating a lower total as a real saving.


Reply
athinker11 Topic starter

Ask how each builder treats allowances: is the amount a cap, or is it reconciled to actual cost? Clarify how unused funds and overruns are handled. Even with the same fee calculation, different rules for credits and overruns can change the final cost.


Reply

The general-conditions list is only comparable if each bid defines what counts as a reimbursable cost. One builder might list temporary utilities as general conditions, while another includes them in a trade price. Reconcile those categories against the contract definitions before comparing totals; otherwise, the lower line may just reflect a different label.