When does an allowance reduce the remaining contingency?

How do you keep the live contingency balance honest when some selection allowances haven’t been finalized? Counting the full allowance as committed could make the available reserve look smaller than it is, but leaving it out entirely could overstate what’s actually free to cover changes.

Would you track the allowance amount as a separate pending commitment, then update contingency only when the selection is approved and the cost is known? And if a selection comes in over allowance, what backup do you ask for, such as the allowance basis and a breakdown of the price difference, before treating the overage as committed?